Sydney�s M6 Motorway wins government approval

Sydney’s M6 Motorway wins government approval

A new tunnel from Arncliffe to Kogarah in Sydney’s south is set to become a reality following NSW Government planning approval.
Branko Miletic
Branko Miletic

06 Jan 2020 1m read View Author

A new tunnel from Arncliffe to Kogarah in Sydney’s south is set to become a reality following NSW Government planning approval.

Planning and Public Spaces minister Rob Stokes said the M6 Stage 1 includes four-kilometre twin tunnels that will connect the New M5 motorway at Arncliffe with President Avenue in Kogarah.

“This project will see more than 2,000 trucks a day taken off local streets, bypass 23 sets of traffic lights, and create thousands of construction jobs,” says Stokes.

“While the tunnel will provide a safer, shorter, more reliable drive between the CBD and Sydney’s south, above ground it will also provide improved access for cyclists and pedestrians.”

The project includes a new shared cycle and pedestrian pathway through Brighton Le-Sands including a bridge over President Avenue linking Rockdale Bicentennial and Scarborough Parks.

A contract will be awarded in December 2020, with construction to begin by early 2022 and the road to open to motorists by the end of 2025.

Image: Supplied

  • Popular Articles
  • Master Plumbers welcomes apprentice incentive but urges government to prioritise employer support
  • The Australian standard: King, Queen and Single beds
  • Discover Australian Urban Design Research Centre’s latest design competition
  • BayleyWard-designed $90M St Kilda apartment project aims high in eco-conscious living